Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review
Jessie Riposo; Megan McKernan; Chelsea Kaihoi
发表日期2014
出版年2014
页码102
语种英语
结论

Some Potential Reasons for Longer Cycle Times or Schedule Delays

  • Infeasible or unrealistic requirements
  • Unstable requirements (e.g., engineering requirements, readiness requirements, reliability and support requirements)
  • Inefficiencies in the process (e.g., serial nature of process and requirements evolution)
  • Excessive technical, manufacturing, or integration risk (general) or program complexity
  • Unanticipated design, engineering, manufacturing, technical difficulty, or technology integration issues
  • Overly optimistic assumptions/expectations
  • Immature technology
  • Concurrency in complicated programs
  • Prototyping
  • Deficient test planning or testing inefficiencies
  • Funding instability or budget cuts
  • Lack of focus on schedule or inadequate schedule management
  • Overly optimistic assumptions/expectations in cost and schedule estimates
  • Personnel issues
  • Competition

Some Potential Ways to Remedy Schedule Challenges

  • Stable and realistic initial requirements, especially at the engineering level
  • Better collaboration between the program management and end-user communities (with proper management)
  • Proper management of flexible requirements
  • Use of mature/demonstrated technology to ensure a high level of maturity before production
  • Employment of "agile" methods that can easily adapt to changes in software development
  • Prototyping
  • Use of commercially derived items
  • Use of the commercial practice of freezing the design before the production contract award
  • Use of the commercial practice of reducing the design's complexity
  • Stable funding
  • Adequate test funds (hardware, modeling and simulation)
  • Acquisition of the same number of units but in larger, more economical quantities in the production phase
  • Development and maintenance of a comprehensive and realistic master schedule
  • Involvement of the test community in all program phases
  • Use of integrated product teams
  • Realistic schedule estimates
  • Senior leadership support
摘要
  • This report could provide a starting point for further research or consideration, such as critical analysis or an assessment of the strengths or weaknesses of the claims made in the literature, by government acquisition professionals, oversight organizations, and the analytic community.
主题Military Acquisition and Procurement ; Military Logistics ; Military Technology ; United States Department of Defense
URLhttps://www.rand.org/pubs/research_reports/RR455.html
来源智库RAND Corporation (United States)
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/107831
推荐引用方式
GB/T 7714
Jessie Riposo,Megan McKernan,Chelsea Kaihoi. Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review. 2014.
条目包含的文件
文件名称/大小 资源类型 版本类型 开放类型 使用许可
x1495316369165.jpg(9KB)智库出版物 限制开放CC BY-NC-SA浏览
RAND_RR455.pdf(636KB)智库出版物 限制开放CC BY-NC-SA浏览
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
百度学术
百度学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
必应学术
必应学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
相关权益政策
暂无数据
收藏/分享
文件名: x1495316369165.jpg
格式: JPEG
文件名: RAND_RR455.pdf
格式: Adobe PDF

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。