| Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review |
| Jessie Riposo; Megan McKernan; Chelsea Kaihoi
|
发表日期 | 2014
|
出版年 | 2014
|
页码 | 102
|
语种 | 英语
|
结论 |
Some Potential Reasons for Longer Cycle Times or Schedule Delays- Infeasible or unrealistic requirements
- Unstable requirements (e.g., engineering requirements, readiness requirements, reliability and support requirements)
- Inefficiencies in the process (e.g., serial nature of process and requirements evolution)
- Excessive technical, manufacturing, or integration risk (general) or program complexity
- Unanticipated design, engineering, manufacturing, technical difficulty, or technology integration issues
- Overly optimistic assumptions/expectations
- Immature technology
- Concurrency in complicated programs
- Prototyping
- Deficient test planning or testing inefficiencies
- Funding instability or budget cuts
- Lack of focus on schedule or inadequate schedule management
- Overly optimistic assumptions/expectations in cost and schedule estimates
- Personnel issues
- Competition
Some Potential Ways to Remedy Schedule Challenges- Stable and realistic initial requirements, especially at the engineering level
- Better collaboration between the program management and end-user communities (with proper management)
- Proper management of flexible requirements
- Use of mature/demonstrated technology to ensure a high level of maturity before production
- Employment of "agile" methods that can easily adapt to changes in software development
- Prototyping
- Use of commercially derived items
- Use of the commercial practice of freezing the design before the production contract award
- Use of the commercial practice of reducing the design's complexity
- Stable funding
- Adequate test funds (hardware, modeling and simulation)
- Acquisition of the same number of units but in larger, more economical quantities in the production phase
- Development and maintenance of a comprehensive and realistic master schedule
- Involvement of the test community in all program phases
- Use of integrated product teams
- Realistic schedule estimates
- Senior leadership support
|
摘要 |
- This report could provide a starting point for further research or consideration, such as critical analysis or an assessment of the strengths or weaknesses of the claims made in the literature, by government acquisition professionals, oversight organizations, and the analytic community.
|
主题 | Military Acquisition and Procurement
; Military Logistics
; Military Technology
; United States Department of Defense
|
URL | https://www.rand.org/pubs/research_reports/RR455.html
|
来源智库 | RAND Corporation (United States)
|
资源类型 | 智库出版物
|
条目标识符 | http://119.78.100.153/handle/2XGU8XDN/107831
|
推荐引用方式 GB/T 7714 |
Jessie Riposo,Megan McKernan,Chelsea Kaihoi. Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review. 2014.
|
文件名:
|
x1495316369165.jpg
|
格式:
|
JPEG
|
文件名:
|
RAND_RR455.pdf
|
格式:
|
Adobe PDF
|
除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。