Building New Gas Transportation Infrastructure in the EU – what are the rules of the game?
Katja Yafimava
发表日期2018-07-19
出版年2018
页码2
语种英语
概述Although the EU has called over the past decade for gas pipeline promoters to ‘respect EU rules’, these rules had either not been established or were not clear. It was not until March 2017 that a legally binding regulatory framework for the development of incremental (new) pipeline capacity was established, in the form of the […]
摘要Although the EU has called over the past decade for gas pipeline promoters to ‘respect EU rules’, these rules had either not been established or were not clear. It was not until March 2017 that a legally binding regulatory framework for the development of incremental (new) pipeline capacity was established, in the form of the Capacity Allocation Mechanisms Network Code (CAM NC). However, the CAM NC did not resolve all the problematic issues fully, as prior to its adoption many new pipelines had been developed under a patchwork of TEP exemptions, Open Season procedures, and Intergovernmental Agreements. In addition, the CAM NC left important regulatory specificities for the TSOs and NRAs to decide, thus enabling them to develop capacity allocation methods which differ across the EU. Thus, the problem of the regulatory treatment of incremental capacity – created under diverse frameworks with varying degrees of consistency – has not been fully resolved at the EU level and uncertainty remains in respect of its future treatment. This problem has been exacerbated by the ongoing politicization of the EU regulation, particularly in respect of all Russian pipelines but especially Nord Stream 2.  This paper concludes that those pipeline projects initiated prior to the CAM NC’s entry into force should proceed under the rules which were in place at the time of their initiation. Although the EC and the regulatory authorities might be tempted to request some changes in respect of their regulatory treatment – particularly where this differs from what would have been required under the CAM NC – this temptation should be resisted, as further changes would unnecessarily increase (already very significant) uncertainty and complexity. This complexity, together with the lack of clarity associated with the regulatory framework for incremental capacity, suggests that very few major new pipelines will be built in the EU in the future, apart from TAP and EUGAL and the Baltic Pipe, as well as those pipelines needed for connecting the second string of Turkish Stream with European markets. This is because it will be much easier for those wishing to bring additional gas to Europe to do so via LNG import terminals.
主题Country and Regional Studies ; Energy Policy ; Energy Security ; Gas ; Gas Programme
关键词auction Baltic Pipe EC EUGAL exemption Governance IGA Incremental capacity Nord Stream 2 NRA OPAL open season PCI Pipelines Regulation security TAP Third Gas Directive TSO Yamal-Europe
URLhttps://www.oxfordenergy.org/publications/building-new-gas-transportation-infrastructure-eu-rules-game/
来源智库Oxford Institute for Energy Studies (United Kingdom)
引用统计
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/312575
推荐引用方式
GB/T 7714
Katja Yafimava. Building New Gas Transportation Infrastructure in the EU – what are the rules of the game?. 2018.
条目包含的文件
文件名称/大小 资源类型 版本类型 开放类型 使用许可
Building-New-Gas-Tra(6160KB)智库出版物 限制开放CC BY-NC-SA浏览
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Katja Yafimava]的文章
百度学术
百度学术中相似的文章
[Katja Yafimava]的文章
必应学术
必应学术中相似的文章
[Katja Yafimava]的文章
相关权益政策
暂无数据
收藏/分享
文件名: Building-New-Gas-Transportation-Infrastructure-in-the-EU-what-are-the-rules-of-the-game.pdf
格式: Adobe PDF
此文件暂不支持浏览

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。