Quantifying Siting Difficulty: A Case Study of U.S. Transmission Line Siting
Shalini Vajjhala; Paul S. Fischbeck
发表日期2006-02-22
出版年2006
页码DP 06-03
语种英语
摘要

The worldwide demand for new energy infrastructures has been paralleled in recent years by the increasing difficulty of siting major facilities. Siting difficulty is the subject of widespread discussion, but because of the complexity of the problem, potential solutions are not obvious or well understood. This paper presents a two-step policy-level framework that first develops an empirical measure of siting difficulty and then quantitatively assesses its major causes. The approach is based on the creation and aggregation of four siting indicators that are independent of the common causes and localized effects of siting problems. The proposed framework is demonstrated for the case of U.S. transmission line siting. Results of the analyses reveal significant variations in state siting difficulty and industry experts’ perceptions of its dominant causes, with implications for the long-term success of Regional Transmission Organizations (RTOs) and knowledge transfer among siting professionals in the deregulated industry.

The process of finding the right locations for energy facilities—power plants, wind farms, and liquefied natural gas terminals, to name a few—has become more and more difficult in recent years. As major energy projects have grown in size and complexity so have the problems associated with siting them. Because siting difficulty is such a broad problem and one that affects a variety of industries, solutions are not obvious or well understood. To date, the focus has been mostly on extreme examples—like Cape Wind, a proposal for a new wind power farm in Nantucket Sound—and there has been little comprehensive analysis of siting issues.

In her new discussion paper "Quantifying Siting Difficulty: A Case Study of U.S. Transmission Line Siting," RFF Fellow Shalini Vajjhala makes an important step toward addressing this gap. She develops a clear characterization of the siting problem for the example of power lines in the United States. Using a two-tier framework, her paper first answers the question, how difficult is siting?, and then investigates, what makes siting difficult?

Siting projects bring together engineering considerations, such as structural and mechanical requirements; economic constraints, including costs, tradeoffs, and investment options; regulatory requirements, including environmental permits; and public concerns, such as planning for public participation and involving affected communities. Siting difficulty, as it is defined here, includes any combination of obstacles in facilities planning and construction processes: public opposition; environmental, topographic, and geographic constraints; interagency coordination problems; and local, state, and federal regulatory barriers to permitting, investment, and/or construction.

Siting difficulty nowadays is almost synonymous with phrases used to describe widespread public opposition, including NIMBY (not in my backyard) or BANANA (build absolutely nothing anywhere near anything). However, the problem is even more complex than these acronyms suggest. Vajjhala finds that power line siting difficulty varies significantly across the United States Different states are affected by different combinations of siting constraints that could eventually impact long-term regional transmission planning and construction.

In the wake of recent events, like the 2005 Gulf Coast hurricane season, typical siting problems have become even more extreme, and the issue has taken on greater urgency in the face of political and environmental uncertainties related to the security of energy supplies, viability of financing options, and even eventual ownership of facilities in deregulated industries. By developing a measure of siting difficulty that is independent of the common causes and localized effects of siting problems, this research gives structure to a critical and ongoing national debate.

As more parties become involved in siting projects, technical solutions and policy solutions show increasing signs of diverging. This is especially relevant when considering the growing attention to developing new renewable energy projects. In another new discussion paper "Siting Renewable Energy Facilities: A Spatial Analysis of Promises and Pitfalls," Vajjhala builds on the measure of transmission-line siting difficulty developed here to evaluate renewable resource potential. Overall, successful development of both traditional and alternative energy programs requires a sound strategy for managing siting problems. This paper serves as an initial bridge between the quantitative and qualitative issues affecting siting and breaks down the causes of siting problems into manageable pieces for evaluation and planning.

主题Energy and Electricity ; Environmental Economics Topics
URLhttp://www.rff.org/research/publications/quantifying-siting-difficulty-case-study-us-transmission-line-siting
来源智库Resources for the Future (United States)
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/40822
推荐引用方式
GB/T 7714
Shalini Vajjhala,Paul S. Fischbeck. Quantifying Siting Difficulty: A Case Study of U.S. Transmission Line Siting. 2006.
条目包含的文件
条目无相关文件。
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Shalini Vajjhala]的文章
[Paul S. Fischbeck]的文章
百度学术
百度学术中相似的文章
[Shalini Vajjhala]的文章
[Paul S. Fischbeck]的文章
必应学术
必应学术中相似的文章
[Shalini Vajjhala]的文章
[Paul S. Fischbeck]的文章
相关权益政策
暂无数据
收藏/分享

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。