Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review
Jessie Riposo; Megan McKernan; Chelsea Kaihoi
发表日期2014-04-30
出版年2014
语种英语
结论

Some Potential Reasons for Longer Cycle Times or Schedule Delays

  • Infeasible or unrealistic requirements
  • Unstable requirements (e.g., engineering requirements, readiness requirements, reliability and support requirements)
  • Inefficiencies in the process (e.g., serial nature of process and requirements evolution)
  • Excessive technical, manufacturing, or integration risk (general) or program complexity
  • Unanticipated design, engineering, manufacturing, technical difficulty, or technology integration issues
  • Overly optimistic assumptions/expectations
  • Immature technology
  • Concurrency in complicated programs
  • Prototyping
  • Deficient test planning or testing inefficiencies
  • Funding instability or budget cuts
  • Lack of focus on schedule or inadequate schedule management
  • Overly optimistic assumptions/expectations in cost and schedule estimates
  • Personnel issues
  • Competition

Some Potential Ways to Remedy Schedule Challenges

  • Stable and realistic initial requirements, especially at the engineering level
  • Better collaboration between the program management and end-user communities (with proper management)
  • Proper management of flexible requirements
  • Use of mature/demonstrated technology to ensure a high level of maturity before production
  • Employment of "agile" methods that can easily adapt to changes in software development
  • Prototyping
  • Use of commercially derived items
  • Use of the commercial practice of freezing the design before the production contract award
  • Use of the commercial practice of reducing the design's complexity
  • Stable funding
  • Adequate test funds (hardware, modeling and simulation)
  • Acquisition of the same number of units but in larger, more economical quantities in the production phase
  • Development and maintenance of a comprehensive and realistic master schedule
  • Involvement of the test community in all program phases
  • Use of integrated product teams
  • Realistic schedule estimates
  • Senior leadership support
摘要

This report summarizes a selection of the defense acquisition literature from the 1960s to the present on potential sources of prolonged acquisition cycle times and schedule growth, as well as potential opportunities for improvement. It presents the range of possible causes of schedule-related problems and various recommendations cited for improving schedules by various authors and organizations. This report does not provide critical analysis or an assessment of the strengths or weaknesses of the claims made in the literature. Rather, it provides a starting point for further research or consideration by government acquisition professionals, oversight organizations, and the analytic community. We identified the following reasons for schedule delays in the literature: (1) the difficulty of managing technical risk (e.g., program complexity, immature technology, and unanticipated technical issues), (2) initial assumptions or expectations that were difficult to fulfill (e.g., schedule estimates, risk control, requirements, and performance assumptions), and (3) funding instability. The most commonly cited recommendations for reducing cycle time and controlling schedule growth in the literature are strategies that manage or reduce technical risk. Some of those recommendations include using incremental fielding or evolutionary acquisition strategies, developing derivative products (rather than brand-new designs), using mature or proven technology (i.e., commercial, off-the-shelf components), maintaining stable funding, and using atypical contracting vehicles.

目录
  • Chapter One

    Background and Motivation

  • Chapter Two

    Sources of Schedule Growth

  • Chapter Three

    Improving Schedule Performance

  • Chapter Four

    Conclusions

  • Appendix

    A Case Study in Fulfilling an Urgent Operational Need: The MRAP Acquisition Program

主题Military Acquisition and Procurement ; Military Logistics ; Military Technology ; United States Department of Defense
URLhttps://www.rand.org/pubs/research_reports/RR455.html
来源智库RAND Corporation (United States)
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/522470
推荐引用方式
GB/T 7714
Jessie Riposo,Megan McKernan,Chelsea Kaihoi. Prolonged Cycle Times and Schedule Growth in Defense Acquisition: A Literature Review. 2014.
条目包含的文件
文件名称/大小 资源类型 版本类型 开放类型 使用许可
RAND_RR455.pdf(619KB)智库出版物 限制开放CC BY-NC-SA浏览
x1495316369165.jpg.p(4KB)智库出版物 限制开放CC BY-NC-SA浏览
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
百度学术
百度学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
必应学术
必应学术中相似的文章
[Jessie Riposo]的文章
[Megan McKernan]的文章
[Chelsea Kaihoi]的文章
相关权益政策
暂无数据
收藏/分享
文件名: RAND_RR455.pdf
格式: Adobe PDF
文件名: x1495316369165.jpg.pagespeed.ic.5n3JVF1Vvx.jpg
格式: JPEG

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。