Air Force Major Defense Acquisition Program Cost Growth Is Driven by Three Space Programs and the F-35A: Fiscal Year 2013 President's Budget Selected Acquisition Reports
Robert S. Leonard; Akilah Wallace
发表日期2014-12-17
出版年2014
语种英语
结论

Continuing Major Defense Acquisition Programs (MDAPs) Have Higher Average Cost Growth than Those That Are Complete

  • Average cost growth in all acquisition metrics except development is substantially higher in continuing Air Force MDAPs than those that are now complete.
  • Three continuing space programs with extreme cost growth — Space-Based Infrared System, High Component; Advanced Extremely High Frequency; and Evolved Expendable Launch Vehicle (EELV) — drive the higher cost growth in the group of continuing MDAPs. However, in dollar terms, cost growth in the Air Force portion of the F-35 program (F-35A) is by far the largest of all programs.
  • Thus far, there is minimal cost growth in MDAPs begun in the past ten years that have substantial Air Force funding.
  • Four MDAPs in aggregate are expected to consume a large fraction of annual Air Force MDAP acquisition funding in the coming 20 years: F-35A, EELV, KC-46A, and the Long-Range Strike Bomber.
摘要

During the past four decades, the military services and the Office of the Secretary of Defense (OSD) have managed hundreds of very large weapon system acquisition programs. These programs, designated Major Defense Acquisition Programs (MDAPs), account for more than 40 percent of weapon-system acquisition funding appropriated by Congress. RAND maintains an internal database of costs and schedules for these programs, as reported in Selected Acquisition Reports (SARs) dating back to the 1960s.

,

In this report, researchers analyze cost growth in Air Force–managed MDAPs. Differing definitions of cost growth provide differing insights into program outcomes. The analysis focuses on those MDAPs that contain the highest levels of development activity and that, at a minimum, have proceeded through the acquisition process to a point at which a portion of the production units envisioned at the program's Milestone (MS) B were produced and delivered to the warfighter. These MDAPs are broken into two groups: continuing and complete.

,

Controlling costs in continuing MDAPs is essential to the overall affordability of Air Force modernization plans. A handful of ongoing and recently terminated programs account for substantially higher cost growth in recent Air Force programs compared with complete programs. Cost growth to date in four continuing large-dollar programs must be contained to ensure affordability of the Air Force's long-term investment plans.

目录
  • Chapter One

    Selected Acquisition Report Data and Analytics

  • Chapter Two

    Analysis of Major Defense Acquisition Programs with Substantial Air Force Funding

  • Chapter Three

    Findings for Major Defense Acquisition Programs with Substantial Air Force Funding

主题Fighter Aircraft ; Military Acquisition and Procurement ; Military Budgets and Defense Spending ; United States Air Force
URLhttps://www.rand.org/pubs/research_reports/RR477.html
来源智库RAND Corporation (United States)
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/522641
推荐引用方式
GB/T 7714
Robert S. Leonard,Akilah Wallace. Air Force Major Defense Acquisition Program Cost Growth Is Driven by Three Space Programs and the F-35A: Fiscal Year 2013 President's Budget Selected Acquisition Reports. 2014.
条目包含的文件
文件名称/大小 资源类型 版本类型 开放类型 使用许可
RAND_RR477.pdf(1169KB)智库出版物 限制开放CC BY-NC-SA浏览
x1495316370594.jpg.p(3KB)智库出版物 限制开放CC BY-NC-SA浏览
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Robert S. Leonard]的文章
[Akilah Wallace]的文章
百度学术
百度学术中相似的文章
[Robert S. Leonard]的文章
[Akilah Wallace]的文章
必应学术
必应学术中相似的文章
[Robert S. Leonard]的文章
[Akilah Wallace]的文章
相关权益政策
暂无数据
收藏/分享
文件名: RAND_RR477.pdf
格式: Adobe PDF
文件名: x1495316370594.jpg.pagespeed.ic.5LKUyiVIry.jpg
格式: JPEG

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。