Extreme Cost Growth: Themes from Six U.S. Air Force Major Defense Acquisition Programs
Mark A. Lorell; Robert S. Leonard; Abby Doll
发表日期2015-10-06
出版年2015
语种英语
结论

Premature Approval at Milestone B

  • The six Air Force Major Defense Acquisition Programs (MDAPs) examined were not ready for approval at Milestone B (MS B).
  • Five of the six programs examined were characterized by insufficient technology maturity and high integration complexity at MS B.
  • Many of the programs chose unrealistically optimistic cost estimates at MS B that underestimated the challenges of incorporating commercially derived technologies, even though more realistic independent cost estimates were available.

Suboptimal Acquisition Strategies and Program Structure

  • In all six programs, acquisition strategies and program structures were adopted that lacked adequate processes for managing risk through incrementalism and provision of appropriate oversight and incentives for the prime contractor.
  • Four of the programs were not ready for approval at MS C; use of a combined MS B/C milestone or premature award of MS C took place prior to the achievement of adequate production article design stability.
摘要

This report identifies and characterizes conditions present in six U.S. Air Force Major Defense Acquisition Programs (MDAPs) experiencing extreme cost growth, using case study analysis. This report is a companion to Air Force Major Defense Acquisition Program Cost Growth Is Driven by Three Space Programs and the F-35: Fiscal Year 2013 President's Budget Selected Acquisition Reports (RR-477-AF, 2014), which analyzed cost growth trends in current U.S. Air Force MDAPs using Selected Acquisition Report (SAR) data. The case study analysis provided in this document is based on government program documentation and publically available open source materials, as well as interviews with program officials and subject matter experts.

,

The authors find that the key common attributes among the six programs with extreme cost growth can be grouped into two broad areas: (1) premature approval of Milestone B and (2) suboptimal acquisition strategies and program structure. They offer two broad recommendations for improving cost and schedule outcomes for Air Force MDAPs: (1) Establish credible baseline cost estimates at MS B to provide realistic baseline metrics for accurately measuring real cost growth, and (2) develop, refine, and implement robust evolutionary or incremental acquisition strategies and policies that reduce and control technological and programmatic risk, unless timely operational need has clear priority over cost savings.

目录
  • Chapter One

    Introduction

  • Chapter Two

    Case Studies

  • Chapter Three

    Summary Findings and Observations

主题Military Acquisition and Procurement ; Military Budgets and Defense Spending ; United States Air Force
URLhttps://www.rand.org/pubs/research_reports/RR630.html
来源智库RAND Corporation (United States)
资源类型智库出版物
条目标识符http://119.78.100.153/handle/2XGU8XDN/522865
推荐引用方式
GB/T 7714
Mark A. Lorell,Robert S. Leonard,Abby Doll. Extreme Cost Growth: Themes from Six U.S. Air Force Major Defense Acquisition Programs. 2015.
条目包含的文件
文件名称/大小 资源类型 版本类型 开放类型 使用许可
RAND_RR630.pdf(2243KB)智库出版物 限制开放CC BY-NC-SA浏览
x1497377855562.jpg.p(1KB)智库出版物 限制开放CC BY-NC-SA浏览
个性服务
推荐该条目
保存到收藏夹
导出为Endnote文件
谷歌学术
谷歌学术中相似的文章
[Mark A. Lorell]的文章
[Robert S. Leonard]的文章
[Abby Doll]的文章
百度学术
百度学术中相似的文章
[Mark A. Lorell]的文章
[Robert S. Leonard]的文章
[Abby Doll]的文章
必应学术
必应学术中相似的文章
[Mark A. Lorell]的文章
[Robert S. Leonard]的文章
[Abby Doll]的文章
相关权益政策
暂无数据
收藏/分享
文件名: RAND_RR630.pdf
格式: Adobe PDF
文件名: x1497377855562.jpg.pagespeed.ic.9Ym1HAoE9-.jpg
格式: JPEG

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。